Our Projects

Renewable Energy

S. NoProject NameProject DescriptionClientStatus
1Feasibility Study for Identification of Solar, Wind, and Geothermal Energy Corridors in AJ&KPrepared a detailed feasibility study identifying viable solar, wind, and geothermal energy corridors across Azad Jammu & Kashmir, covering resource assessment, site screening, and technical recommendations to support renewable energy development in the region.PDO AJKOngoing
2Development of Energy Master Plan for Gilgit Baltistan (NPAK) EU-FundedPrepared a GIS-based energy master plan for GB under the EU-funded Energy Plus program, assessing renewable resources, demand forecasts, and investment needs with policy recommendations.NPAKOngoing
3Development of Energy Master Plan for Chitral (NPAK) EU-FundedPrepared an integrated energy master plan for Chitral under the EU-funded Energy Plus program, covering hydropower, solar, biomass, and geothermal options.NPAKOngoing
4Design, Construction Supervision, and Contract Management for 34.5 MW Hydropower Project Ghowari, Ghanche, GBPrepared detailed design drawings, BOQs, cost estimates, tender designs, and bidding documents, and provided construction supervision, QA/QC, and contract management for the Ghowari hydropower project.Water and Power Department, GBOngoing
51.0 MW Solar PV at Duikar Altit, Nasirabad and HunzaPrepared feasibility study and tender design for two 1 MW solar PV projects in Hunza District, including resource assessment, grid stability review, and procurement support.GIZCompleted
6Feasibility for 100 MW Solar PV Project at Konodas Top, GilgitPrepared feasibility study and tender design for a 100 MW solar PV project, assessing site conditions, solar potential, and grid stability for GB.GIZCompleted
7Feasibility for 600 MW Solar PV Project near Muzaffargarh, PunjabPrepared feasibility and environmental assessment inputs for a large-scale solar PV project, supporting utility-scale renewable energy planning in Punjab.GIZCompleted
8Management and Supervision – Punjab Ujaala Program, Solarization of 4,200 SchoolsSupported implementation and quality/cost/schedule monitoring for solar PV systems across 4,200 schools in Punjab, including operation and maintenance handover design.Govt. of PunjabCompleted
9Feasibility Study for Solar Generation in Gilgit-BaltistanScreened GB for solar irradiation and suitable PV sites, preparing feasibility, design, grid connection options, and PC-1 support.Govt. of Gilgit-BaltistanCompleted
10Feasibility Study for 21 MW Hydropower Project on Gilgit River at Sonikot, GilgitCarried out feasibility study including site investigations, engineering design, and environmental study for a proposed hydropower project on Gilgit River.Water and Power Department, GBCompleted

Highways and Roads

S. NoProject NameProject DescriptionClientStatus
1Design Review and Construction Supervision of Road from Gorikote-Astore to Shagharthang-SkarduProvided design review and construction supervision for a strategic road link between Astore and Skardu, improving regional connectivity and tourism access.C&W Department, Gilgit BaltistanOngoing
2Construction Supervision of Inter-Provincial Connectivity Economic Corridor through GB and AJ&K (Thallichi GB – Shounter AJK)Supervised design review and construction supervision of Thallichi GB – Shounter AJK road under a strategic inter-provincial connectivity corridor linking Gilgit-Baltistan and Azad & Jammu Kashmir.C&W Department, Gilgit BaltistanOngoing
3Construction of Road from Pissan to Hoper Nagar (40 Km), incl. Bridges and Allied Structures (Shahrah-e-Nagar)Provided design review, construction supervision, and contract administration for a 40 km road corridor, including bridges, retaining walls, and allied structures.C&W Department, Gilgit BaltistanOngoing
4Feasibility Study of Hunza Bypass RoadPrepared feasibility study inputs for the proposed Hunza bypass Road, supporting early-stage road planning for improved mobility.C&W Department, Gilgit BaltistanCompleted

Environment and Climate Change

S. NoProject NameProject DescriptionClientStatus
1ESIA for Gorikote-Astore to Shagharthang-Skardu Road ProjectPrepared the Environmental and Social Impact Assessment for the Shagarthang to Gorikot road, evaluating environmental and social considerations to support design review and construction supervision for this key connectivity and tourism access corridor.C&W Department, Gilgit BaltistanCompleted
2ESIA for Thallichi GB – Shounter AJK (AVR) Road ProjectConducted the Environmental and Social Impact Assessment for the Thallichi GB – Shounter AJK road, assessing the project’s environmental and social footprint along this key connectivity corridor between Gilgit-Baltistan and Azad Jammu & Kashmir, to support design review and construction supervision.C&W Department, Gilgit BaltistanCompleted
3ESIA for Shahrah-e-Nagar Road ProjectCarried out the Environmental and Social Impact Assessment for the 40 km road corridor, evaluating potential impacts on land, communities, and the surrounding environment to inform the design review and construction supervision process.C&W Department, Gilgit BaltistanCompleted
4Feasibility Study for an Investment in a Green Infrastructure Guarantee Facility in PakistanPrepared feasibility study covering financial, operational, and environmental analysis for a proposed green infrastructure guarantee facility.KfWCompleted
5Development of a Climate Change Adaptation Plan for Districts Astore, Chitral, and GhizerPrepared district-level climate adaptation plans integrating risk assessments, community inputs, and an M&E framework for mountain districts in GB and KP.AKAHPCompleted
6Development of District-Level Climate Adaptation Plan for Five Districts in Gilgit-BaltistanPrepared climate adaptation plans for Gilgit, Astore, Nagar, Kharmang, and Ghanche, including risk assessments, GIS hazard mapping, and nature-based solutions.WWFCompleted
7Development of District-Level Climate Adaptation Plan for Upper and Lower Chitral, KPPrepared adaptation plans for Upper and Lower Chitral under WWF’s WRAP program, addressing flood, drought, and GLOF risks.WWFCompleted
8Climate Change Strategy and Action Plan for Gilgit-BaltistanDeveloped climate change strategy and action planning support addressing adaptation priorities and institutional climate response needs for GB.EPA-GBCompleted
9IEE/ESIA for 5 MW Hydropower Project, Chitral, KPPrepared Environmental Assessment documentation for a 5 MW hydropower project in Chitral, including associated substation and transmission line components.Water and Power Department, GBCompleted
10IEE/ESIA for 15 MW Sakarkoi Hydropower ProjectPrepared Environmental and Social Assessment documentation supporting compliance review for the Sakarkoi hydropower project in GB.Water and Power Department, GBCompleted
11IEE/ESIA for 16 MW Naltar Hydropower Project, GilgitPrepared Environmental and Social Assessment documentation supporting safeguard planning for the Naltar hydropower project.Water and Power Department, GBCompleted
12IEE/ESIA 20 MW Hydropower Project, Hanzel, GilgitConducted Environmental and Social Impact Assessment for the Hanzel hydropower project, assessing environmental and social considerations to support implementation monitoring and compliance oversight for the GB Water and Power Department.Water and Power Department, GBCompleted
13IEE/ESIA for 34.5 MW Hydropower Project Ghowari, Ghanche, GBConducted the Environmental and Social Impact Assessment for the Ghowari hydropower project, assessing environmental and social considerations to support detailed design, tender documentation, and construction supervision.Water and Power Department, GBCompleted
14IEE for 600 MW solar PV Muzaffargarh, PunjabPrepared Environmental Assessment Inputs for a large-scale solar PV project, supporting utility-scale renewable energy planning in Punjab.GIZCompleted
15IEE for 100 MW solar PV Konodas Top Gilgit-BaltistanConducted the Environmental and Social Impact Assessment for the 100 MW solar PV project in Gilgit-Baltistan, assessing site conditions, land use, and social and environmental considerations to support project feasibility and tender designGIZCompleted
16IEE for 1 MW solar PV Duikar, Hunza, Gilgit-BaltistanConducted the Environmental Impact Assessment for two 1 MW solar PV projects in Hunza District, assessing environmental considerations to support the feasibility study, tender design, and procurement process.GIZCompleted
17IEE for Solarization of 4200 schools in central PunjabPrepared the Initial Environmental Examination for the solarization of 4,200 schools across Punjab, assessing environmental and social considerations for the Government of Punjab’s solar PV rollout program.Govt. of PunjabCompleted
18Strengthen E&S Risk Management in NGC ProjectsPrepared E&S Operational Policies, Procedures, and Tools for NGC, and provided training to the company staffAFDCompleted

Monitoring and Evaluation

S. NoProject NameProject DescriptionClientStatus
1Monitoring & Evaluation Consultant for 20 MW Hydropower Project, Hanzel, GilgitMonitored implementation progress, quality, and compliance for the Hanzel hydropower project, supporting GB Water and Power Department with Monitoring and Evaluation oversight.Water and Power Department, GBOngoing

Trainings and Capacity Building

S. NoProject NameProject DescriptionClientStatus
1Building Capacities of Women in the Energy Sector in PakistanConducted gender assessment and delivered technical and leadership training for women in the energy sector, supporting national gender mainstreaming policy.ADBCompleted
2Scaling Sustainable Energy Management Systems in Pakistan Cities (REEE SCALE II)Mainstreamed energy management practices in municipal organizations, developing ISO 50001-based training materials and a capacity-building strategy.GIZCompleted
3O&M Training of Hydropower StaffProvided training to the Water and Power Department GB staff on O&M aspects of the hydropower projectsKfWCompleted
4E&S Operational Policy and ProceduresProvided training to the NG staff in Lahore, Islamabad, Multan, and Hyderabad on Operational Policy, Procedures and ToolsAFDCompleted